I frequently switch between scheduling projects in days or hours. Recently I've been having an issue with my OD/RD calculating off of a 24 hour calendar even though a 8 hour calendar is applied. For example, I'll schedule the activity 8 hours, but when I show the OD/RD in days, it shows 0D. Is this a user setting I might have changed somewhere?