Hi, I have made mid-project baseline on a project to track from now and till end of project. But I experience that the new baseline is not synced with the period actual earned value as I would expect.
Why does Primavera not do the calculation based on remaining unit value, and mirror the history? Is there a applicaton setting that I have missed out?