Hi all,
sorry for this newbye question...

Suppose a job having a next_date for execution at 04/04/2007 04:00, at 04/04/2007 03:00 the db is shutted down and at 04/04/2007 06:00 is started up.

I repeat the scedule again:
04/04/2007 03:00 - Db shutdown
04/04/2007 04:00 - Job should run, but db is down
04/04/2007 06:00 - Db startup
??/??/???? ??:?? - When will the job run?

What happen at the job, when will it be executed, will it be broken and failures increased?

thanks a lot

aldo