Primavera P6 Professional 21 Edition

User_0SO6VOct 23 2021

We use P6 at our power plant to schedule our planned outages. We have created our schedule and have just started executing work. Every time I complete an activity (enter in actual finish date) the successors immediately pull up to Project start date. I removed the schedule preference to use Expected Finish. What am I missing? Thanks.