HI, we try to use the manufacturing plan with demands scheduled itens with forecast demand, but the system don't explode the dependent demand....
All my itens is MRP planning
45020 -> product
48400 -> ingredient
48435 -> ingredient
........



Formule:


The workbench don't show the ingredients, just the product.

Anybody knows the cause?