Skip to Main Content

Integration

Announcement

For appeals, questions and feedback about Oracle Forums, please email oracle-forums-moderators_us@oracle.com. Technical questions should be asked in the appropriate category. Thank you!

Labor unit hours not calculating from activity duration

User_A9I5PAug 22 2022

Hello-
I am a beginner with P6, so forgive me if this is a simple answer.
My activity is set to 5 days but when I assign it a resource, budgeting labor units appears as 15h, and not 40h which makes no sense. How to I get it to auto calculate 40h based on 5 day duration?
Capture.JPG

Comments
Post Details
Added on Aug 22 2022
0 comments
249 views