Hi All,
I have 3 Solaris servers part of the EPM 11.1.2.1 environment:
Server1.company.com:
- Foundation services, APS, EAS
Server2.company.com:
- Essbase Server, Essbase Studio Server.
- Installation done on a SAN disk using user ID hypadmin
Server3.company.com:
- *Nothing installed here*.
- Its the standby server in case Server2 goes down.
Note: I couldn't find any documentation for my below approach... So please understand the risk involved before attempting the same.
Pre-disaster recovery:
- I copy the home directory of hypadmin from Server2 to Server3.
During disaster recovery:
- I update the Essbase server host name from Server2.company.com to Server3.company.com and similarly update the opmn.xml file.
- Finally mount the SAN onto Server2 and start up the services.
--
Has anyone done the same..? Have you faced any issues? Is there a better way of doing this?
Thanks
Regards,
Kent