Hi All,

I have scheduled a batch script to refresh the cube that's runs CubeRefresh.cmd utility. The job status shows complete and job console in workspace shows refresh status as completed.

But when I check with the essbase outline, its not updated with the changes. Planning log shows nothing so which log do I check to know what is the issue?

Has anyone faced similar issue?

I'm on Planning 11.1.2.4 on premise and have two separate servers for Application and Essbase Database.