MaheshGxMar 23 2012 — edited Mar 23 2012
Hi,

I have a package MASTER consisting of another 10 packages in it.and in digram it shows like one after another i.e. id 1 ok then 2 ok the 3 and so on....
But when i execute MASTER package, it starts execution of 2-3 packages simultaneously.

I am unable to find the root cause of this concurrent running.
What i want is packages should run one after another as specified in diagram rather than running concurrenntly.

Help apprecited.

Thanks,
Mahesh
This post has been answered by Sutirtha Roy on Mar 23 2012
Jump to Answer