hi all,
is it possible to make a certain step, which is added to an activity, the driver for the successor, in stead of just the 100% completed status.
for example:
Activity "A" had 6 steps (in the followng order) to be completed.
startup
progress up until Internal Dicipline Check
Internal Discipline Check
issued for review
receive comments from client
final issue
I want my next activity to start after my issued for review step had finished.
Is this possible, and if yes, how is it achieved?
thanks you!
kind regards,
Erik Kuipers