We operate in a project and task environment with planning groups utilized for pegging. We run a constrained plan by enforcing demand due dates. I have Purchase Order supply for a part across a few tasks and I have demand across the same tasks. In the screen shot below, why is the order with the earlier promised date getting a "reschedule out" message (Its pegging to the 1.1.2.04.05.112 demand) while the later promised material has a "reschedule in" message? Why is ASCP not pegging the earliest available supply to the earliest requirement?
Thanks in advance!
Larry