Ability to prevent creation of new activities on an active project.

Shewangi KoulMar 17 2026 — edited Mar 24 2026

During Project Close-Out activities, project managers need the ability to prevent users from creating new activities against an existing project, while still allowing currently open activities to continue and be completed/closed. We request an enhancement in WACS to allow the same.

Currently, there does not appear to be an out-of-the-box way in WACS to prevent new activities from being created for a Project that is still active.